Direct answer
The short answer
Estimate the complete project cost, add setup costs, the working capital needed and a justified contingency, then subtract confirmed cash available for the project. That gives an initial external funding gap. Check when each payment falls due in a cash-flow forecast. The gap is not a recommended borrowing amount, an affordability result or a finance offer.
Key points
- List the whole project, including delivery, installation, professional and setup costs.
- Model when income and expenditure actually enter or leave the bank account.
- Separate costs by purpose and expected duration instead of assuming one facility must cover everything.
- Do not count an unconfirmed grant, sale, contribution or facility as available cash.
Build the complete funding picture
Start with every cash requirement, then deduct the contribution available from the business.
- Purchase or project cost
The agreed price and the items included in it.
- Add setup and transaction costs
Include relevant fees, implementation and other one-off costs.
- Add working capital and contingency
Allow for the cash needed to operate and a realistic buffer.
- Deduct the available contribution
The remaining gap is the estimated external funding requirement.
A planning estimate does not establish how much a provider will lend. Check payment dates and avoid counting the same cost twice.
Worked example: calculating a £200,000 funding gap
This invented example shows the method for a business investment. It is not a customer case, a quotation or evidence that these costs can be financed. VAT, taxes and finance charges are excluded here and must be added where relevant to the actual cash plan.
| Budget item | Amount |
|---|---|
| Equipment and other project purchases | £200,000 |
| Delivery, setup and professional costs | £15,000 |
| Working capital needed during the early operating period | £25,000 |
| Contingency for identified uncertainties | £10,000 |
| Total planning requirement | £250,000 |
| Less confirmed business cash available for this project | −£50,000 |
| Initial external funding gap | £200,000 |
£200,000 + £15,000 + £25,000 + £10,000 − £50,000 = £200,000.
The cash contribution must be available when needed without leaving existing business commitments unfunded. A provider may exclude some costs, offer a different amount or decline the request. Any remaining gap still needs to be resolved before committing.
Use the business funding requirement calculator to organise your own figures. For an equipment-specific breakdown, see the plant and machinery purchase example.
List the complete project
Begin with the main purchase or transaction, then add the costs required to make it operational. Examples can include delivery, installation, professional fees, recruitment, initial stock, equipment, software, licences and launch or relocation expenses. Not every cost will be financeable, but leaving it out does not make it disappear.
Check when the money is needed
Put receipts and payments into the week or month when the money is expected to reach or leave the bank. An invoice date or a planned sale is not necessarily the receipt date. The British Business Bank’s cash-flow forecast guide explains this approach.
Opening cash + receipts − payments = closing cash. Carry that closing figure into the next period and identify the lowest balance before assuming new finance. Keep proposed finance visible as an unconfirmed assumption until its availability and release conditions are established.
Use the project budget to identify costs and the forecast to place them in time. Do not add the same payroll, stock or installation costs twice by treating both the budget and the forecast shortfall as separate expenses. Keep any unspent contingency as a buffer rather than a second cost.
Separate costs by purpose and duration
Group property, machinery, vehicles, stock, invoices and temporary working-capital needs separately. This makes it easier to consider whether one or more potential structures may be relevant without assuming that every cost belongs in one facility.
Subtract only confirmed contributions
Record the cash the business will genuinely contribute and label the source. Treat a grant, asset sale, tax recovery, investor contribution or other facility as unavailable until it is sufficiently confirmed. The planning estimate should remain usable if an assumption changes.
Test a slower or more expensive scenario
Recalculate with a delay, cost increase or later customer payment. In the example above, suppose a slower start increases the working-capital requirement from £25,000 to £45,000. Keeping the other assumptions unchanged, the total becomes £270,000 and the external gap becomes £220,000 after the £50,000 contribution.
That is an extra £20,000 to resolve. It does not automatically mean borrowing more is appropriate or available. Review the timing, scope, contribution and alternatives with suitable professional support before making a commitment.
Turn the calculation into a short funding brief
| Field | What to record |
|---|---|
| Purpose | What the project will achieve and which costs it includes. |
| Budget and assumptions | Itemised costs, dated quotations and items still estimated. |
| Contribution | The amount, source and date cash will be available. |
| Funding gap | The initial gap and which costs you want a provider to consider. |
| Timing | Payment milestones and the lowest forecast cash balance. |
| Weaker case | What changes if delivery or customer receipts are delayed. |
Keep the supporting records for a provider discussion if requested. Bene’s initial enquiry does not require financial documents. For an acquisition, use the business acquisition funding checklist to separate purchase price, transaction costs and cash needed after completion.
Keep the estimate separate from a provider decision
Explain when the investment should begin contributing cash and how repayments might be supported if revenue is delayed. A provider will make its own assessment of affordability, security, eligibility and the amount—if any—it is prepared to offer.
Common questions
Questions about this guide
Should setup and installation costs be included?
Include costs needed to make the project operational in the planning schedule, such as delivery, installation and professional fees. Their accounting, tax and finance treatment can vary, so label each cost clearly.
Should an expected grant or asset sale reduce the requirement?
Only subtract a contribution when it is sufficiently confirmed. Keep uncertain grants, sales, investments or other facilities visible as assumptions so the plan still works if they change.
Is the calculator result the amount a business should borrow?
No. It is a planning estimate only. It does not calculate affordability, eligibility, repayments, approval or a finance offer, and a provider will make its own assessment.
Primary sources
Sources reviewed for this guide
- How to calculate business start-up costsStart Up Loans
- Capital v revenue expenditure toolkit: acquisition, improvement and alteration of assetsHM Revenue & Customs
- Preparing for funding applicationsBusiness.gov.uk
- How to create a cash-flow forecast in four stepsBritish Business Bank
- Business loansBritish Business Bank
External sources provide general context and do not endorse Bene Finance or establish that a funding option is available.
This guide provides general information only and is not financial advice or a guarantee that finance will be available.
